Recent design-build project for a Fortune 500 chemical manufacturer. We replaced an existing boiler and pump system with high efficiency 6,000 BTU condensing hot water boilers (18,000 BTU total) saving the customer 52,000+ Therms per year amounting to $52,325 saved per year. We redesigned and repiped the system, eliminating 3 pumps and saving an additional 16,000+ KWH. The customer also received a $75,000 utility rebate from the power company. #boilers #hotwaterboilers #boilersystems #sustainablemechanicalengineering

Recent design-build project for a Fortune 500 chemical manufacturer. We replaced an existing boiler and pump system with high efficiency 6,000 BTU condensing hot water boilers (18,000 BTU total) saving the customer 52,000+ Therms per year amounting to $52,325 saved per year.

We redesigned and repiped the system, eliminating 3 pumps and saving an additional 16,000+ KWH. The customer also received a $75,000 utility rebate from the power company.

#boilers #hotwaterboilers #boilersystems #sustainablemechanicalengineering

Recently installed Heat Recovery Skid at Cedar’s Mediterranean Foods captures high grade heat from two (2) 125 HP Air Compressors with heat-of-compression Air Dryers. It is used to preheat boiler feed and process hot water. The system qualified for a significant National Grid rebate. #SustainableMechanicalEngineering #AirCompressorHeatRecovery #ThermalRecovery #CustomHeatRecoverySkid #NationalGridRebate

Recently installed Heat Recovery Skid at Cedar’s Mediterranean Foods captures high grade heat from two (2) 125 HP Air Compressors with heat-of-compression Air Dryers. It is used to preheat boiler feed and process hot water. The system qualified for a significant National Grid rebate.
#SustainableMechanicalEngineering #AirCompressorHeatRecovery #ThermalRecovery #CustomHeatRecoverySkid #NationalGridRebate

Recently-installed heat exchanger skid to convert open process cooling system to a closed loop. This eliminates fouling in Freudenberg’s molding machines, increasing the cooling effect, increasing production output, and reducing maintenance costs. #ConvertOpenCoolingTowertoClosedSystem #EliminateCoolingTowerFouling #CleanUpOpenCoolingTower #ProcessCooling

Recently-installed heat exchanger skid to convert open process cooling system to a closed loop. This eliminates fouling in Freudenberg’s molding machines, increasing the cooling effect, increasing production output, and reducing maintenance costs.

#ConvertOpenCoolingTowertoClosedSystem #EliminateCoolingTowerFouling #CleanUpOpenCoolingTower #ProcessCooling

Our team fabricated this intricate skid that will be used to test the performance of hydraulic pumps at various suction and discharge pressures and temperatures. It will handle both mineral and synthetic oils, and will soon be installed for a top secret U.S. military project. #TemperatureControlSkid #HydraulicTestingSkid #MechanicalEngineering

Our team fabricated this intricate skid that will be used to test the performance of hydraulic pumps at various suction and discharge pressures and temperatures. It will handle both mineral and synthetic oils, and will soon be installed for a top secret U.S. military project.
#TemperatureControlSkid
#HydraulicTestingSkid
#MechanicalEngineering

President Joe D’Ambrosio speaks at National Grid event

President Joe D’Ambrosio speaks at National Grid event

Last week, IMEC president and director of engineering, Joe D’Ambrosio, was invited to speak to a group of the largest manufacturers in Rhode Island about the conception and design of efficient mechanical systems. Joe’s focus was on taking a scientific approach to solving mechanical challenges, and designing and building systems that benefit everyone by dramatically cutting energy costs and reducing the carbon footprint of manufacturing facilities.

read more
IMEC wins 2015 Innovative Project of Year Award from AEENE

IMEC wins 2015 Innovative Project of Year Award from AEENE

On Wednesday May 6, president and director of engineering Joe D’Ambrosio, Sr. and team accepted the award for Innovative Energy Project of the Year from the Association of Energy Engineers of New England at the Annual New England Energy Awards at the Embassy Suites Hotel in Waltham. D’Ambrosio also made a presentation about the challenges, solutions, and energy efficiency features of the winning heat recovery project for Cains Foods.

read more
Freudenberg in Bristol, NH embarks on massive $3 million overhaul of plant heating system with design and implementation by IMEC.

Freudenberg in Bristol, NH embarks on massive $3 million overhaul of plant heating system with design and implementation by IMEC.

With the assistance of the mechanical engineering design/build firm IMEC in Ayer, MA, the Freudenberg factory’s legacy system, which employs obsolete high pressure steam boilers and #6 fuel oil, is being scrapped in favor of leading-edge design and technology. The plant’s entire heating load will be replaced with efficient liquefied natural gas (LNG), initially phased in by employing propane as a bridge fuel.